General Assist Technical Reference
VRF PCB Replacement
Addressing, capacity check and return-to-service procedure
STOP — do not energise a replacement PCB until its settings have been verified.
A replacement VRF PCB is not plug-and-play. Every DIP switch, rotary switch, address, connector and relevant field setting must be recorded from the old PCB and correctly applied to the replacement board.
Why this matters
Incorrect PCB configuration can cause duplicate or missing addresses, incorrect refrigerant-circuit identification, communication errors, incorrect master/slave operation, terminal-resistor faults, failed capacity checks and repeat service attendance.
Before you start
Required equipment and information
✓ Exact installation or service manual for the affected model
✓ Approved replacement PCB with verified part number and revision
✓ Lock-out/tag-out equipment and approved voltage tester
✓ Camera or phone for clear before-and-after photographs
✓ ESD controls and insulated hand tools
Mandatory evidence before removing the old PCB
☐ Wide photograph showing the complete electrical box and cable routing
☐ Close-up photographs showing every DIP and rotary switch position
☐ Clear photographs of all plugs, terminals, earths and wire positions
☐ Written record of IU address, REF address, outdoor address, master/slave and terminal resistor
☐ Original fault code, symptoms and diagnostic basis for PCB replacement
PCB replacement procedure
Indoor PCB address settings
Where an indoor PCB uses rotary switches, both the indoor-unit address and refrigerant-circuit address must match the removed PCB or approved addressing schedule.
Example
Indoor address 23: set IU AD ×10 = 2 and IU AD ×1 = 3.
Refrigerant circuit 07: set REF AD ×10 = 0 and REF AD ×1 = 7.
Addressing rules: addresses must be unique; the REF address must correspond with the correct outdoor system; automatic addressing requirements must be checked in the exact model manual; and manually addressed systems must remain consistent with central-controller or BMS records.
J-X family reference
Applicability warning: The sequences below apply to the published J-IVS / J-IV / J-IVL commissioning process. Other generations may use different menus and switch combinations. Always confirm the exact model manual.
Automatic indoor addressing — F3-11 (not requirement most of the time as indoors are already set)
1. Press MODE / EXIT once; F1 flashes.
2. Press SELECT until F3 displays, then press ENTER.
3. Select 11 and hold ENTER for at least 3 seconds. “run” displays.
4. LED105 shows successfully addressed units; LED104 shows failed units.
5. Resolve failures, repeat the process, then press ENTER when all units succeed.
6. Power reset all indoor units for 2 minutes.
Indoor capacity / connection check — F3-12 (required)
1. Enter F3 as above.
2. Select 12 and hold ENTER for at least 3 seconds. “run” displays.
3. Read the detected indoor-unit quantity and compare it with the site.
4. Press SELECT to display the connected-capacity ratio.
5. Confirm both figures and press ENTER. A successful result displays PASS.
6. If Err displays, open the error details, rectify the cause and repeat.
Do not return the system to service when
✕ Any switch or address setting remains unverified
✕ The detected indoor-unit count does not match the site
✕ The capacity ratio is incorrect or unexplained
✕ Addressing returns a failure or duplicate-address result
✕ An active or unexplained communication error remains
Technician completion checklist
☐ Before-and-after PCB photographs attached
☐ All connectors and earths secure
☐ All DIP and rotary switch settings verified
☐ Readdressing completed where required
☐ Detected indoor-unit count matches the site
☐ Capacity ratio confirmed and PASS displayed
☐ Heating and/or cooling test operation completed
☐ No active or unexplained fault remains
Where the SOP and model-specific manufacturer instructions differ, stop and contact GENERAL Technical Support.
For authorised service personnel only.